Antecedentes

1. Introduction

 

This is the Terms of Reference for the UNDP-GEF Midterm Review (MTR) of the full-sized project titled Improving Connectivity in the Central Forest Spine Landscapes (IC-CFS) (PIMS#4594) implemented by the Forestry Department of Peninsular Malaysia, which is to be undertaken in June – December 2021. The project started on 18 March 2014 and is in its sixth year of implementation. The project is scheduled to end on 31 December 2021 after granted a nineteenth month extension. In December 2017, an Independent Rapid Review was commissioned to address the lack of progress to project outputs. Following to the review, an adaptive management plan was developed in consultation with implementing agencies, resulting in adjustments applied to the Strategic Results Framework.

 

Under the conditional approval received from UNDP in May 2020, the project may be extended until 31 December 2022 (subject to meeting the key milestones in 2021) and a final twelve-month extension until 31 December 2023 (subject to meeting the key milestones in 2022). The MTR process must follow the guidance outlined in the document Guidance for Conducting Midterm Reviews of UNDP-Supported, GEF-Financed Projects (see http://web.undp.org/evaluation/documents/guidance/GEF/mid-term/Guidance_Midterm%20Review%20_EN_2014.pdf

 

2. Project Background and Information

 

The Project “Improving Connectivity in the Central Forest Spine Landscape” (PIMS#4594) is a US$ 10.86 million GEF-funded project initiated in 2014 that is designed to address the fragmentation of Peninsular Malaysia’s Central Forest Spine (CFS) – valued for its megadiversity of species, including the only remaining population of Malayan tigers, and supplies of water for 90% of the state’s population. Recognising that Malaysia’s rapidly growing economy and illegal trade in forest and wildlife resources are eroding the country’s natural capital and in response to forest fragmentation being identified in the 2005 National Physical Plan as a major threat to the conservation and maintenance of biodiversity, the Government of Malaysia formulated the CFS Master Plan (MP) in 2008 to restore ecological connectivity between forest fragments.

 

This project contributes to implementing the Master Plan by focusing specifically on conserving biodiversity and ecosystem services in three key forest landscapes, identified to be both critical for tiger conservation in the National Tiger Conservation Action Plan as well as priority linkages in the CFS Master Plan: Belum-Temenggor Forest Complex, Taman Negara Forest Complex and Endau-Rompin Forest Complex. In addition to restoring connectivity between these forest complexes, the project will strengthen the national and local institutional frameworks for CFS management and law enforcement, support sustainable forest landscape management and secure sustainability of funding for conservation through the diversification of funding sources and mainstreaming of ecosystem service values into land use planning.

 

The project objective is to increase federal and state level capacity to execute the CFS Master Plan through the implementation of sustainable forest landscape management plans in three pilot sites, financed sustainably through the diversification and increased allocation of funds for conservation. It is designed to remove the barriers to the establishment of a landscape approach to biodiversity management. The project comprises of three components:

 

Component 1. Planning, compliance monitoring and enforcement framework for integrated forest landscape management;

Component 2. Sustainable forest landscape management of three priority forest landscapes within the CFS; and

Component 3. Diversification of financing sources for conservation.

See the signed project document at

https://www.my.undp.org/content/dam/malaysia/docs/Central%20Forest%20Spine%20Final%20Pro%20Doc.pdf

 

Table 1 shows the project basic information:

Table 1: Basic information for the “Improving Connectivity in the Central Forest Spine Landscape” Project

 

Project Title

Improving Connectivity in the Central Forest Spine Landscape (PIMS#4594)

ATLAS ID

00077143

Country, Region

Malaysia, Asia Pacific

Date Project Document Signed

18 March 2014

Project date

Start

Planned end

 

18 March 2014

31 December 2021 (pending conditional approval up to 31 December 2022)

Project budget

$10.86 million

Funding source

Global Environment Facility (GEF)

Implementing partner

Forest Department Peninsular Malaysia

 

The project started on 18 March 2014 and is currently in its sixth year of implementation. Due to a mix of implementation challenges including capacity issues, federal-state relations on forest protection, as well as various phases of COVID-19 movement restrictions imposed since early 2020. The project is scheduled to end on 31 December 2021. Under the conditional approval received from GEF in May 2020, the project may be extended until 31 December 2022, and a final twelve-month extension until 31 December 2023, subjected to project meeting the key milestones in 2022.

 

Since 4 January 2020 until 6 May 2021, Malaysia has recorded 424,376 confirmed cases of COVID-19 with 1,591 deaths. On 18 March 2020, Government of Malaysia officially enforced the Movement Control Order (MCO) under the Prevention and Control of Infectious Diseases Act 1988 and the Police Act 1967. The order prohibited mass movements, gatherings and restrictions on the entry of all tourists and foreign visitors into the country. Although restrictions were relaxed when cases subsided, Government of Malaysia have again announced the enforcement of MCO across several states from 6 May until 17 May 2021 following the rise of cases nationwide. Although the prolonged movement restrictions have extensively hindered the progress of the project’s implementation, the delays had been addressed by having more virtual meetings and discussions and localizing the activities at State and districts level to ensure the implementation can progress with minimum disruption.

 

3. MTR Purpose

 

The MTR will assess progress towards the achievement of the project objectives and outcomes as specified in the Project Document and programme outcomes as stipulated in the Country Programme Action Plan (CPAP) 2016 – 2020 between UNDP and the Government of Malaysia, and assess early signs of project success or failure with the purpose of identifying the necessary changes to be made in order to set the project on-track to achieve its intended results. The MTR will also review the project’s strategy and its risks to sustainability. The MTR is also one of the key milestones under the project’s conditional approval for its extension before another 12-month extension can be considered and approved.

 

4. MTR Approach & Methodology

The MTR report must provide evidence-based information that is credible, reliable and useful.

The MTR team will review all relevant sources of information including documents prepared during the preparation phase (i.e. PIF, UNDP Initiation Plan, UNDP Social and Environmental Screening Procedure (SESP), the Project Document, the revised Strategic Results Framework[1], Environmental and Social Safeguards Policy (ESSP), project reports including Independent Rapid Review (IRR), Annual Project Review/PIRs, Quarterly Progress Reports, Adaptive Management Action Plan, extension request and approval package, adaptive management update reports, project budget revisions, national strategic and legal documents, list of relevant stakeholders and any other materials that the team considers useful for this evidence-based review. The MTR team will review the baseline GEF focal area Core Indicators/Tracking Tools submitted to the GEF at CEO endorsement, and the midterm GEF focal area Core Indicators/Tracking Tools that must be completed before the MTR field mission begins.

 

The MTR team is expected to follow a collaborative and participatory approach[2] ensuring close engagement with the project team, government counterparts (the GEF Operational Focal Point, Project Board Chairperson, National Project Director, etc.), the UNDP Country Office, the Nature, Climate and Energy (NCE) Regional Technical Advisor, direct beneficiaries, and other key stakeholders.

Engagement of stakeholders is vital to a successful MTR.[3] Stakeholder involvement should include interviews with stakeholders who have project responsibilities, including but not limited to  executing agencies, senior officials, project team consists of project manager, state project coordinators, monitoring & evaluation officer, communications officer; key experts and consultants in the subject area, Project Board/Steering Committee, Adaptive Management Advisory Panel (AMAP), project stakeholders, academia, local government and CSOs, etc. Additionally, the MTR team (only for national team members) may be required to conduct field missions to project sites in Perak, Pahang and Johor.

The specific design and methodology for the MTR should emerge from consultations between the MTR team and the above-mentioned parties regarding what is appropriate and feasible for meeting the MTR purpose and objectives and answering the evaluation questions, given limitations of budget, time, data, movement restrictions and safety guidance in view of the on-going COVID-19 pandemic. The MTR team must, however, use gender-responsive methodologies and tools and ensure that gender equality and women’s empowerment, as well as other cross-cutting issues and SDGs are incorporated into the MTR report.

The final methodological approach including interview schedule, field visits and data to be used in the MTR must be clearly outlined in the Inception Report and be fully discussed and agreed between UNDP, stakeholders and the MTR team. 

As of 11 March 2020, the World Health Organization (WHO) declared COVID-19 a global pandemic as the new coronavirus rapidly spread to all regions of the world. International travel to Malaysia has been restricted since 18 March 2020 and travels within the country is also restricted in selected States and areas. If it is not possible to travel to or within the country for the MTR mission, then the MTR team should develop a methodology that will conduct the MTR virtually and remotely, including the use of remote interview methods and extended desk reviews, data analysis, surveys and evaluation questionnaires. This should be detailed in the MTR Inception Report and agreed with the Commissioning Unit.

 

If all or part of the MTR is to be carried out virtually then consideration should be taken for stakeholder availability, ability or willingness to be interviewed remotely. In addition, their accessibility to the internet/computer may be an issue as many government and national counterparts may be working from home. These limitations must be reflected in the final MTR report. 

 

If a data collection/field mission is not possible then remote interviews may be undertaken through telephone or online (skype, zoom etc.). International consultant will work remotely with national evaluators’ support in the field, provided it is safe for the national evaluators to operate and travel in compliance with the local Standard Operating Procedures (SOPs) for COVID.

 

The MTR Gender and Community Development Specialist will perform the key tasks as follows:

 

  • Conduct a document review of project related documents i.e. Country Programme Action Plan (CPAP) 2016 – 2020 between UNDP and Government of Malaysia, Project Identification Form (PIF), UNDP Initiation Plan, Project Document, Environmental and Social Safeguard Policy (ESSP), Project Inception Report, Independent Rapid Review report, Adaptive Management Action Plan, Revised Strategic Results Framework, Project Implementation Reviews, Finalized GEF focal area Tracking Tools, Project Steering Committee meeting minutes, Key Performance Indicators, Financial and Administration guidelines used by Project Team, project operational guidelines, manuals and systems, etc.; provided by UNDP Malaysia Country Office and Project Team.
  • Facilitate in MTR inception workshop to clarify their understanding of the objectives and methods of the MTR, producing the MTR inception report thereafter by providing expertise and knowledge on social and gender mainstreaming in biodiversity, wildlife conservation and sustainable forest landscape management.
  • Coordinate and conduct field mission with other MTR team members that consist of interviews with stakeholders who have project responsibilities and site visits to Kuala Lumpur, Gerik (Perak), Merapoh (Pahang) and Kota Tinggi (Johor).
  • Assess the following four categories of project progress based on the Guidance for Conducting Midterm Reviews of UNDP-Supported, GEF-Financed Projects for requirements on ratings. No overall rating is required.
  • Produce relevant chapters of a draft and final MTR report as assigned by the MTR Lead Evaluator.
  • Plan with Lead Evaluator and National Evaluator and present the final MTR report in the MTR Concluding Stakeholder Workshop, particularly on the aspect of social and gender mainstreaming.

 

The National Evaluator will perform the key tasks as follows:

 

  • Conduct a document review of project related documents i.e. Country Programme Action Plan (CPAP) 2016 – 2020 between UNDP and Government of Malaysia, Project Identification Form (PIF), UNDP Initiation Plan, Project Document, Environmental and Social Safeguard Policy (ESSP), Project Inception Report, Independent Rapid Review report, Adaptive Management Action Plan, Revised Strategic Results Framework, Project Implementation Reviews, Finalized GEF focal area Tracking Tools, Project Steering Committee meeting minutes, Key Performance Indicators, Financial and Administration guidelines used by Project Team, project operational guidelines, manuals and systems, etc.; provided by UNDP Malaysia Country Office and Project Team.
  • Facilitate in MTR inception workshop to clarify their understanding of the objectives and methods of the MTR, producing the MTR inception report thereafter by providing expertise and knowledge in the field of biodiversity and ecosystems, and sustainable forest landscape management in Malaysia.
  • Coordinate and conduct field mission with other MTR team members. The mission will consist of interviews with stakeholders who have project responsibilities and site visits to Kuala Lumpur, Gerik (Perak), Merapoh (Pahang) and Kota Tinggi (Johor).
  • Assess the following four categories of project progress based on the Guidance for Conducting Midterm Reviews of UNDP-Supported, GEF-Financed Projects for requirements on ratings. No overall rating is required.
  • Produce relevant chapters of a draft and final MTR report as assigned by MTR Lead Evaluator.
  • Plan with Lead Evaluator and Gender & Community Development Specialist to present the final MTR report in the MTR Concluding Stakeholder Workshop.

 

[1] The original SRF was revised and endorsed by Project Steering Committee in 2019 following the Independent Rapid Review’s recommendations.  

[2] For ideas on innovative and participatory Monitoring and Evaluation strategies and techniques, see UNDP Discussion Paper: Innovations in Monitoring & Evaluating Results, 05 Nov 2013.

[3] For more stakeholder engagement in the M&E process, see the UNDP Handbook on Planning, Monitoring and Evaluating for Development Results, Chapter 3, pg. 93.

Deberes y responsabilidades

 

(E) Conclusions & Recommendations

 

The MTR team will include a section in the MTR report for evidence-based conclusions, in light of the findings.

 

Additionally, the MTR Team is expected to make recommendations to the Project Team. Recommendations should be succinct suggestions for critical intervention that are specific, measurable, achievable and relevant. A recommendation table should be put in the report’s executive summary. See the Guidance for Conducting Midterm Reviews of UNDP-Supported, GEF-Financed Projects for guidance on a recommendation table.

 

The MTR team should make no more than 15 recommendations in total.

 

(F) Ratings

 

The MTR team will include its ratings of the project’s results and brief descriptions of the associated achievements in a MTR Ratings & Achievement Summary Table (Table 3) in the Executive Summary of the MTR report. See Annex E for ratings scales. No rating on Project Strategy and no overall project rating is required.

 

Table 3. MTR Ratings & Achievement Summary Table for Improving Connectivity in the Central Forest Spine Landscapes (IC-CFS)

Measure

MTR Rating

Achievement Description

Project Strategy

N/A

 

Progress Towards Results

Objective Achievement Rating: (rate 6 pt. scale)

 

Outcome 1 Achievement Rating: (rate 6 pt. scale)

 

Outcome 2 Achievement Rating: (rate 6 pt. scale)

 

Outcome 3 Achievement Rating: (rate 6 pt. scale)

 

Etc.

 

Project Implementation & Adaptive Management

(rate 6 pt. scale)

 

Sustainability

(rate 4 pt. scale)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6. Duration of Work

 

The total duration of the National Evaluator will be 50 working days starting 15 July 2021 and shall not exceed six months from when the National Evaluator is hired. The tentative MTR timeframe is as follows:

 

  • 30 June 2021: Application closes
  • 1 – 10 July 2021: Selection of MTR Lead Evaluator and team members
  • 15 – 30 July 2021: Prep the MTR Team (handover of project documents)
  • 1 – 7 August 2021 (5 days): Document review and preparation of MTR Inception Report
  • 8 – 15 August 2021 (3 days): Finalization and validation of MTR Inception Report – latest start of MTR mission
  • 15 – 31 August 2021 (11 days): MTR mission: stakeholder meetings, virtual interviews, field visits (if the travel is permitted)
  • 1 – 8 September 2021 (1 day): Mission wrap-up meeting & presentation of initial findings- earliest end of MTR mission
  • 9 September – 24 September 2021 (12 days): Preparing draft report and consolidating stakeholders’ feedback and comments to the draft report
  • 27 September – 8 October 2021 (3 days): Incorporating audit trail on draft report and finalization of MTR report
  • 11 – 15 October 2021 (3 days): Preparation for management response
  • 15 – 31 October 2021 (2 days): Planning and present the final MTR findings and recommendations at the Concluding Stakeholder Workshop
  • 30 November 2021: Expected date of full MTR completion

 

The start date of contract is 15 July 2021.

 

7.MTR Outputs and Deliverables

As part of the MTR Team, the National Evaluator shall prepare and submit:

 

#

Deliverables

Description

Timing

Responsibilities

1. 

MTR Inception Report

MTR team clarifies objectives and methods of Midterm Review

Approximate date: 15 August 2021 (or

no later than 2 weeks before the MTR mission)

 

MTR team submits to the UNDP Malaysia Country Office and project management

2

Presentation

Initial Findings to project management and UNDP Malaysia Country Office

Approximate date: 8 September 2021

MTR Team presents to UNDP Malaysia Country Office and project management

Draft MTR Report

Full draft report (using guidelines on content outlined in Annex B) with annexes

Approximate date: 24 September 2021

Sent to the UNDP Malaysia Country Office, reviewed by RTA, Project Coordinating Unit, GEF OFP

4

Final Report and PPT slides*

Revised report with audit trail detailing how all received comments have (and have not) been addressed in the final MTR report

Approximate date: 31 October 2021

Sent to the Commissioning Unit

 

*The final MTR report must be in English. If applicable, UNDP Malaysia may choose to arrange for a translation of the report into Malay language – the official language more widely shared by national stakeholders.

 

8. MTR Arrangement

The Commissioning Unit for this project’s MTR is UNDP Malaysia Country Office. UNDP Malaysia will contract the National Evaluator and ensure the timely provision of per diems and travel arrangements within the country for the MTR team, if the travel is permitted. The Project Team will be responsible for liaising with the MTR team to provide all relevant documents, set up stakeholder interviews, and arrange field visits.

 

The Commissioning Unit and Project Team will provide logistic support in the implementation of remote/ virtual meetings if travel to project site is restricted. An updated stakeholder list with contact details (phone and email) will be provided by the Commissioning Unit to the MTR team.

9. Duty Station

All travels within Malaysia will be arranged by UNDP Malaysia and Project Team, if travel is permitted.

 

Travel:

  • Domestic travel to project sites in Gerik (Perak), Merapoh (Pahang) and Kota Tinggi (Johor) will be required during the MTR mission; the COVID-19 travel restrictions permitting.  Depending on the COVID-19 travel restrictions the missions may be organized physically or virtually;  
  • The Basic Security in the Field II and Advanced Security in the Field courses must be successfully completed prior to commencement of travel;
  • Individual Consultants are responsible for ensuring they have vaccinations/inoculations when travelling to certain countries, as designated by the UN Medical Director.
  • Consultants are required to comply with the UN security directives set forth under https://dss.un.org/dssweb/.

Ethics

The MTR team will be held to the highest ethical standards and is required to sign a code of conduct upon acceptance of the assignment. This MTR will be conducted in accordance with the principles outlined in the UNEG ‘Ethical Guidelines for Evaluation’. The MTR team must safeguard the rights and confidentiality of information providers, interviewees and stakeholders through measures to ensure compliance with legal and other relevant codes governing collection of data and reporting on data. The MTR team must also ensure security of collected information before and after the MTR and protocols to ensure anonymity and confidentiality of sources of information where that is expected. The information, knowledge and data gathered in the MTR process must also be solely used for the MTR and not for other uses without the express authorization of UNDP and partners.

 

Scope of Price Proposal and Schedule of Payments

Financial Proposal:

  • Financial proposal must be “all inclusive” and expressed in a lump-sum for the total duration of the contract. The term “all inclusive” implies all cost (professional fees, travel costs, living allowances etc.);
  • For duty travels, the UN’s Daily Subsistence Allowance (DSA) rates should provide indication of the cost of living in a duty station/destination.
  • The lump sum is fixed regardless of changes in the cost components.

 

Schedule of Payments:

20% payment upon satisfactory delivery and acceptance of the final MTR Inception Report and approval by the UNDP Malaysia Country Office

40% payment upon satisfactory delivery and acceptance of the draft MTR report to the UNDP Malaysia Country Office

40% payment upon satisfactory delivery and acceptance of the final MTR report and approval by the UNDP Malaysia Country Office and delivery of completed Audit Trail

 

Criteria for issuing the final payment of 40%:

  • The final MTR report includes all requirements outlined in the MTR TOR and is in accordance with the MTR guidance.
  • The final MTR report is clearly written, logically organized, and is specific for this project (i.e. text has not been cut & pasted from other MTR reports).
  • The Audit Trail includes responses to and justification for each comment listed.

 

[1] Consider that the findings and recommendations of this MTR will inform the rating -or not- of a twelve-month conditional extension for this project.

[2] Populate with data from the Log frame and scorecards

[3] Populate with data from the Project Document

[4] If available

[5] Colour code this column only

[6] Use the 6-point Progress Towards Results Rating Scale: HS, S, MS, MU, U, HU

[7] Risks are to be labelled with both the UNDP SES Principles and Standards, and the GEF’s “types of risks and potential impacts”: Climate Change and Disaster; Disadvantaged or Vulnerable Individuals or Groups; Disability Inclusion; Adverse Gender-Related impact, including Gender-based Violence and Sexual Exploitation; Biodiversity Conservation and the Sustainable Management of Living Natural Resources; Restrictions on Land Use and Involuntary Resettlement; Indigenous Peoples; Cultural Heritage; Resource Efficiency and Pollution Prevention; Labor and Working Conditions; Community Health, Safety and Security.

Competencias

Corporate Competencies:

  • Demonstrates integrity by modelling the UN’s values and ethical standards;
  • Promotes the vision, mission, and strategic goals of UNDP;
  • Displays cultural, gender, religion, race, nationality and age sensitivity and adaptability
  • Treats all people fairly without favouritism;
  • Fulfils all obligations to gender sensitivity and zero tolerance for sexual harassment;
  • Demonstrates integrity by modelling the UN’s values and ethical standards.

 

Functional Competencies:

  • Demonstrated understanding of issues related to biodiversity and ecosystems, and sustainable forest landscape management;
  • Excellent communication and analytical skills;
  • Experience with conducting evaluations remotely will be considered an asset.

Habilidades y experiencia requeridas

Qualifications of the Successful Applicants

A team of three independent experts will conduct the MTR - one international team leader (with experience and exposure to projects and evaluations in other regions globally), one national expert from the country of the project and one Gender and Community Development Specialist. 

The selection of Gender and Community Development Specialist will be aimed at maximising the overall “team” qualities in the following: 

Qualifications:

  • A Master’s degree or higher in social science, community development, gender and development studies, or other closely related field (10 points);
  • Experience applying logical framework analysis and SMART targets in project design and management (10 points);
  • Experience working with project evaluation/review for at least 3 years (20 points);
  • Experience working in Malaysia and South-East Asian region (10 points);
  • Work experience in community development, gender and environment for at least 5 years (20 points);
  • Language: fluency in written and spoken English and Malay.

 

DOCUMENTS TO BE INCLUDED WHEN SUBMITTING THE PROPOSALS

Interested individual applicants must submit the following documents/information to demonstrate their qualifications:

  1. Document 1 : Letter of Confirmation of Interest and Availability at https://undp.org/content/dam/malaysia/docs/Procurement/Template%20of%20Letter%20of%20Interest.docx
  2. Document 2: Technical Proposal: of why the individual considers him/herself as the most suitable for the assignment, and a proposed methodology on how they will approach and complete the assignment; (max 1 page)
  3. Document 3: Financial Proposal at https://undp.org/content/dam/malaysia/docs/Procurement/Financial%20Proposal%20Template-Deliverables_MYR_IC2021-017v1.doc? that indicates the all-inclusive fixed total contract price, supported by a breakdown of costs, as per template provided.  If an applicant is employed by an organization/company/institution, and he/she expects his/her employer to charge a management fee in the process of releasing him/her to UNDP under Reimbursable Loan Agreement (RLA), the applicant must indicate at this point, and ensure that all such costs are duly incorporated in the financial proposal submitted to UNDP.  
  4. Document 4: Personal CV or P11 indicating all past experience from similar projects, as well as the contact details (email and telephone number) of the Candidate and at least three (3) professional references  https://undp.org/content/dam/malaysia/docs/Procurement/P11%20for%20Consultant_Optional.docx
  5. Please submit this information in one file as Document 1, 2, 3 and 4.The system will only accept one attachment , please merge all documents and submit as one file.
  6. Applicants must reply to the mandatory questions asked by the system when submitting the application.
  7. Candidates who fail to submit all the information requested above will be disqualified.


How to Apply:

  • Kindly download the Letter of Confirmation of interest and availability, Financial Proposal Template and General Terms & Conditions mentioned below;
  • Read and agree to the General Terms & Conditions (refer to below link);
  • Click the ‘apply’ icon and complete what is required;
  • Scan all documents into 1 pdf folder and then upload;
  • For clarification question, please email to procurement.my@undp.org. The clarification question deadline is three (3) days before the closing. When emailing for clarification questions, please put "MyIC/2021/018"as the subject matter.

 

General terms & conditions to be downloaded:

Reimbursable Loan Agreement (RLA): A legal instrument between UNDP and a Company/institution, according to which, the latter makes available the services of an individual delivering time-bound and quantifiable outputs that are directly linked to payments

Incomplete proposals may not be considered. Only short-listed candidates may be contacted, and successful candidates will be notified.

 

ANNEXES 

1.  Annex A: List of Documents to be reviewed by the MTR Team https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20A_%20List%20of%20Documents%20to%20be%20reviewed%20by%20the%20MTR%20Team.pdf

2.  Annex B: Guidelines on Contents for the Midterm Review Report (The Report length should not exceed 40 pages in total (not including annexes). https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20B_%20Guidelines%20on%20Contents%20for%20the%20Midterm%20Review%20Report.pdf

3.  Annex C: Midterm Review Evaluative Matrix Template http://www.my.undp.org/content/dam/malaysia/docs/Procurement/Annex C_Midterm Review Evaluative Matrix Template.pdf

4.  Annex D: UNEG Code of Conduct for Evaluators/Midterm Review Consultants  (http://www.unevaluation.org/document/detail/100) https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20D_%20UNEG%20Code%20of%20Conduct%20for%20Evaluators%20Midterm%20Review%20Consultants.pdf

5.  Annex E: MTR Ratings and Achievements Summary Table and Rating Scales https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20E_%20MTR%20Ratings%20and%20Achievements%20Summary%20Table%20and%20Rating%20Scales.pdf

6. Annex F: MTR Report Clearance Form  https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20F_%20MTR%20Report%20Clearance%20Form.pdf

7. Annex G: Audit Trail Template http://www.my.undp.org/content/dam/malaysia/docs/Procurement/Annex G_ Audit Trail Template.pdf

8. Annex H: Progress Towards Results Matrix http://www.my.undp.org/content/dam/malaysia/docs/Procurement/Annex H_ Progress Towards Results Matrix.pdf

9. Annex I: GEF Co-Financing Template https://undp.org/content/dam/malaysia/docs/Procurement/Annex%20I_%20GEF%20Co-Financing%20Template.pdf

 

Criteria for Selection of the Best Offer

The award of the contract will be made to the Individual Consultant who has obtained the highest Combined Score and has accepted UNDP’s General Terms and Conditions.  Only those applications which are responsive and compliant will be evaluated. The offers will be evaluated using the “Combined Scoring method” where:

 

  1. The educational background and experience on similar assignments will be weighted a max. of 70%. Only applicants who score a minimum of 50% will be qualified to undertake financial evaluation;
  2. The price proposal will weigh as 30% of the total scoring.

 

The applicant receiving the Highest Combined Score that has also accepted UNDP’s General Terms and Conditions will be awarded the contract.